Power minister warns against vandalism of electricity towers

The Minister of Power, Joseph Tegbe, has warned Nigerians against vandalising electricity infrastructure, saying the destruction of transmission towers is threatening power supply and economic activities across the country.

Tegbe raised the concern on Friday during the commissioning of the upgraded Bauchi Transmission Substation, which was transformed from a 132/33kV facility into a 330/132/33kV substation.

The minister said the destruction of electricity infrastructure would impose additional costs on the government and disrupt businesses, working hours and household activities.

“There is no justification for the destruction and damage of critical national assets. We are getting to the point where people are pulling down towers and blowing up towers,” he said.

“Nothing will benefit us as a nation by destroying these assets because, at the end of the day, it is public resources that we will use to rebuild them.

“The cost of vandalism will be felt through interrupted trade, interrupted electricity supply, disrupted working hours and the hardship it brings to families. Let’s protect these assets and report any form of sabotage or intrusion.”

He called on host communities to take ownership of electricity facilities and support the government in protecting them against vandalism.

Speaking on the substation upgrade, Tegbe said the project was aimed at strengthening the national electricity transmission network and providing additional capacity to meet growing electricity demand in Bauchi State and neighbouring communities.

He said the facility’s transformation capacity had increased to 300MVA at the 330/132kV level and 180MVA at the 132/33kV level.

According to him, the improved facility would enhance electricity supply to Bauchi metropolis, Ningi, Dass, Alkaleri and adjoining communities.

READ ALSO:

“What we are commissioning today is the elevation of an existing transmission facility into a stronger, more capable and strategically important node within the national electricity network,” he said.

The minister said the original substation had an installed capacity of 112.5MVA, comprising 22.5MVA, 30MVA and 60MVA transformers, which became inadequate as electricity demand increased.

He said the upgrade involved installing two 150MVA, 330/132kV transformers and replacing the existing 22.5MVA and 30MVA transformers with two 60MVA units.

The project also included a modern control room, 330kV line bays, additional 33kV outgoing feeders and upgraded control and protection facilities.

Earlier, the Managing Director and Chief Executive Officer of the Transmission Company of Nigeria, Sule Abdulaziz, said the project was awarded in January 2021 to a joint venture comprising MBH Power Limited and Shreem Electric Limited, with funding from the World Bank.

He said the project was completed in June 2026, increasing the substation’s capacity from 112.5MVA to 180MVA at the 132/33kV level, while providing an additional 300MVA capacity at the 330/132kV level.

Abdulaziz said the project was expected to benefit an estimated additional population of 64,800 people and improve electricity supply to residential, commercial and industrial consumers.

He listed Ningi, Dass, Bauchi GRA, Yankari, Nabordo, Dabo Farm and Gubi communities among the areas expected to benefit from the intervention.

The Emir of Bauchi, Rilwanu Sulaimanu, represented by the Waziri of the emirate, Uba Kari, commended the Federal Government for the project and urged residents to report suspicious activities capable of threatening the facility.